Design Scope and Goal Setting
  •  Internal Project Kickoff: October 22, 2021
Workshops
  • Functional Recovery: April 11, 2022
  • Sustainability Metric: September 22, 2022
LFRS Design
  • Phase 1 (UFP-Wall configuration) – Complete
  • Phase 2 (BRB-Wall configuration) – Complete
  • Phase 3 – Under Development
Design Presentation to Project Advisory Committee
  • Phase I and II design meeting: August 12, 2022
    • Follow up meeting: October 25, 2022
Construction Bid Documents
  • Preparation of Construction Drawings – Complete
  • Preparation of Shop Drawings – In progress
Material Procurement
  • In Progress
Shake-table Testing
  • Expected timeline for testing: July – December, 2023